|
With
the opening of a third track on the Harlem line between
Fleetwood and Crestwood, ACRE members are wondering if M-N
is going to pay their 14b and 17b penalty claims?
Let
us review some of the history and newsletters
seeking clarification on 14b payments. In 1999 our officers
during the campaign for the ACRE sent out a newsletter proclaiming
how they achieved numerous understandings with M-N on 14b
payments. We also have a
14b reference guide that was mailed out to the membership
by these officers to keep for future guidance.
Prior
to the 1999 contract with M-N, the only craft to receive
14b payments for going beyond a train's scheduled CP point
was paid solely to Engineers. In the 1999 Contract, Conductors
and Trainman would now receive a penalty payment, a 17b,
for going beyond a train's scheduled CP point. In essence
the entire crew would now receive a penalty payment. This
change to our agreement with M-N helped pave the way for
the ratification of the 1999 contract and for ACRE to become
the bargaining representative for Conductors and Trainman
on M-N.
In
March of 2000, ACRE takes over and has control of our contracts
and the enforcement of our agreements with M-N. To date
our ACRE officers have denied any language changes to the
14b or 17b language contained in our contracts with M-N.
In our recent historic ACRE contract, again no contract
language changes were implemented or voted on, concerning
our 14b or 17b agreements. So now why do we not get paid
for going beyond our turning points like we used to prior
to the ACRE?
Review
the questions from this reference sheet. Question: If my
train is bulletined to turn at CP 25 and instead I am ordered
to turn at CP 26, do I get paid a 14b? Answer: YES.
Currently under the ACRE without any contract
language changes to our agreements, we do not get paid 14b
or 17b claims for this turn. This claim was paid prior to
the ACRE.
What
could have changed over these past four years and caused
ACRE officers not to enforce our contract and work agreements
with M-N?
- Could it be that
ACRE officers are now on the MTA M-N payroll?
- Could it be that
14b and 17b payments became too expensive for M-N? Prior
to 1999 when only Engineers received penalty payments
for a 14b, it would only cost M-N about $90.00 per turn.
Now with Conductors and Trainman receiving penalty payments,
a train going past it's scheduled CP point would cost
M-N between $270.00 and $360.00. If M-N had 10 trains
going beyond their scheduled CP points in any given rush
hour, their costs would have grown from about $900.00
to either $2,700.00 or $3,600.00. Now it is not in M-N's
interest to turn many trains beyond their scheduled CP
points anymore. It now becomes very expensive for M-N
to turn trains beyond their scheduled CP points.
- ACRE officers
claim that the non-payment of these claims stem from a
language interpretation of the rule. We now have to look
at it from M-N's point of view. ACRE calls this interest
based bargaining. When this rule was negotiated we had
turn points instead of CP points. Then as M-N installed
more CP points closer together, it became advantageous
for M-N to turn trains at CP points instead of turn points.
M-N could now turn trains and crews quicker and more often.
Now with CP points becoming to close to each other, we
should now look at the intent of the rule and go back
to turn points. If this is now ACRE officers argument,
then why do they allow M-N to print run books and schedule
trains to turn at CP points instead of turn points? M-N
currently has it both ways.
Using
their 14b reference sheet as our guide, the only thing that
has been compromised is our ACRE officers integrity concerning
the enforcement our contract and work agreements with M-N.
With no contract language changes to our agreements concerning
14b and 17b payments, with ACRE and M-N interpreting the
context of this rule differently, 14b and 17b payments are
now a thing of the past. Who loses out? As usual, the working
ACRE membership does.
Look
at what happened last winter when M-N had equipment shortages
and combined trains and crews worked beyond their scheduled
CP points. ACRE and M-N worked out a deal. Who lost out?
The ACRE membership did. Now crews want to know if they
will be paid 14b and 17b payments for turning at Crestwood
instead of Fleetwood? Crews should speculate that a deal
had already been worked out between M-N and ACRE officers
before this track ever opened. The outcome of this negotiated
settlement should come as no surprise to anyone.
If
this contract language interpretation change has you thinking,
look at what ACRE officers have allowed M-N to do concerning
our sick time agreement. ACRE officers have allowed M-N
to add new constraints and contract language changes concerning
how many times an employee can mark off sick within a specified
time period. Again ACRE officers claim that no contract
language changes were ever made to the sick time agreement.
ACRE members were not informed about any constraints and
did not vote on any contract language changes to our sick
time agreement with the recent historic ACRE contract. So
why is M-N sending out letters of investigation to ACRE
members for marking off sick and using the sick time allocated
in our agreements? A larger and more important concern is
why ACRE officers have their members signing waiver for
marking off sick. Once again interest based bargaining comes
into play. We need to look at it from M-N's point of view.
M-N employees now have a responsibility to and are expected
to come to work every day. Forget why sick time was negotiated
for the membership to begin with. Only M-N concerns count.
In our crafts, when an employee marks off sick, they must
be replaced with another employee. For now, our jobs cannot
blanked. Every train needs at the very least an Engineer
and a Conductor. When employees mark off sick, it costs
M-N money to fill this position. This is one of the main
reasons behind the extra list and the relief list. So if
M-N can intimidate you along with ACRE's blessings into
not using your rights under these agreements, they save
money and can reduce the number of employees needed to maintain
the extra list and greatly reduce relief day work. Without
merit and for convenience, ACRE will point to another crafts
board award to justify there and M-N's position.
What
it all boils down to is this: ACRE officers + MTA pay =
ACRE members work rules being eroded away. In the very near
future, please keep ACRE's interest based bargaining in
mind, when ACRE officers seek a monthly dues increase.
|